About this video: a 200x525 industrial steel building for a precast plant
In this 0:55 video, Jeff Langner of Nuvocon erects a 200x525 Toro industrial steel building, 105,000 sq ft, for a precast concrete plant north of Toronto. He covers the roughly 2.5 million pounds of steel delivered on 72 truckloads, the heavy crane beams inside, and the sandwich panel roof system.
The building is one of Toro's large manufacturing facilities, engineered in-house by Toro's engineering team for heavy cranes. See more industrial and warehouse buildings. Toro doesn't install buildings: this one was erected by Nuvocon.
- 2.5 million pounds of steel. Roughly 2.5 million pounds of steel arrived on 72 truckloads.
- Built for heavy cranes. Heavy crane beams run through the building for the precast production line.
- A sandwich panel roof. The building uses an RTS sandwich panel roof system.
Key moments in the video
Jump to any part of the 0:55 video on YouTube.
- A 200x525 Toro steel buildingJeff Langner introduces the 200x525 building and its roughly 2.5 million pounds of steel.
- 72 truckloads for a precast plantThe steel arrived on 72 truckloads for a plant making tilt-up precast panels.
- Crane beams and a sandwich panel roofHe points out the heavy crane beams and the sandwich panel roof system, two weeks into erection.
Read the video transcript
A 200x525 Toro steel building
0:00 Jeff Langner here with Nuvocon Limited. We're erecting a Toro steel building, 200 feet wide by 525 feet long.
0:10 Roughly two and a half million pounds of steel for this structure.
72 truckloads for a precast plant
0:17 We had 72 truckloads of steel. The purpose of this building is a precast plant for tilt-up precast panels, but the primary purpose of this building is that it's the first building in North America to use an Italian technology.
Crane beams and a sandwich panel roof
0:33 An example of the crane beams right here: there are heavy cranes in this building. It's an RTS roof system, so it's a sandwich panel roof system. Right now we're two weeks into erecting.
Transcript lightly edited for readability. Music-only sections are left out.
The building in this video
A 200x525 Toro industrial steel building, 105,000 sq ft, for a precast concrete plant north of Toronto.
Jeff Langner
Nuvocon, building erectorJeff's crew erected the building, which took roughly 2.5 million pounds of steel delivered on 72 truckloads. He says it is the first building in North America to use an Italian precast technology.
“We're erecting a Toro steel building, 200 feet wide by 525 feet long.”
Built for heavy cranes
Crane beams and roof systemHeavy crane beams run through the building for the precast production line, and the roof is an RTS sandwich panel system. At the time of filming, the crew was two weeks into erection.
“There are heavy cranes in this building.”
“Roughly two and a half million pounds of steel for this structure.”

Every Toro building is engineered in-house for your site's snow, wind and seismic loads and comes with engineer-stamped drawings. Buildings are made in 30+ manufacturing facilities certified to standards including CSA A660, CWB, AISC and AWS D1.1. Engineering is led by Noah Sinclair, our in-house structural engineer.
Questions about large industrial steel buildings
Still unsure? Price your building and a building specialist will walk you through it.
How big is this building?
The building is 200 feet wide by 525 feet long, or 105,000 sq ft. Jeff Langner says it took roughly 2.5 million pounds of steel, delivered on 72 truckloads.
Can a steel building carry overhead cranes?
Yes. This building has heavy crane beams for its precast production line. Toro engineers crane systems into the building design, so share your crane loads with your building specialist early.
What roof system does this building use?
Jeff says it uses an RTS roof system, a sandwich panel roof.
Who erected the building?
Nuvocon erected this building. Toro doesn't install buildings. Every kit is engineered for bolt-together assembly by the customer or a contractor they choose.
Do I get engineer-stamped drawings?
Yes. Every Toro building comes with engineer-stamped drawings for your location, which you can use for your building permit.
How much does an industrial steel building cost?
Toro steel building kits start at $19 USD per sq ft in the U.S. and $26 CAD per sq ft in Canada. Your site's loads and codes, along with size, framing system, openings and options, have a big impact on the final price, so reach out for pricing on your specific building.