What does an 80x100 steel building look like as a welding shop in Thunder Bay? It is an 8,000 sq ft clear-span red iron shop, 80 ft wide, 100 ft long and 27 ft to the eave, engineered for a 60.6 psf ground snow load and two 5-ton overhead cranes under the 2015 National Building Code of Canada. Toro designed, engineered and supplied this 80x100 steel building for a local welding and fabrication business.
It is a pre-engineered red iron steel building with tapered clear-span frames, the system our customers choose for manufacturing facilities, shops and industrial work. Toro has supplied pre-engineered steel buildings for more than 40 years and sold more than 100,000 of them, and every one is engineered for the snow, wind and seismic loads at its exact site. This 80x100 steel building shipped with drawings sealed by a licensed Ontario engineer, and it was assembled locally on the owner's foundation.
Key takeaways
- Engineered for Northern Ontario snow. Designed for a 60.6 psf ground snow load and a 56.9 psf roof snow load, with drifting considered.
- Crane-ready from day one. Frames, crane beams and bracing designed for two 5-ton top-running cranes on a full-length runway.
- Room to grow. 8,000 sq ft clear span, five 20 ft bays and an expandable endwall for future bays.
80x100 steel building specs
The building as ordered and engineered.
| Detail | 80x100 Steel Building Welding Shop |
|---|---|
| Location | Thunder Bay, Ontario, Canada |
| Building | Pre-engineered red iron clear-span steel building |
| Size | 80 ft wide x 100 ft long |
| Eave height | 27 ft |
| Floor area | 8,000 sq ft, plus a 25 x 30 ft attached office |
| Roof | 2:12 gable, standing seam |
| Bays | Five 20 ft bays |
| Cranes | Designed for two 5-ton top-running cranes |
| Doors | Three 14 x 16 ft and one 12 x 12 ft framed openings, three insulated walk doors |
| Insulation | 12 in. roof, 8 in. walls, full-height liner panels |
| Colours | Charcoal Gray walls and roof, Ash Gray trim |
| Code | 2015 National Building Code of Canada |
| Designed | 2019 to 2020 |
Price a building like this
Tell us your size, site and use, and a Toro building consultant will come back with an engineered, code-compliant quote.
Watch: from sealed drawings to finished welding shop
This 80x100 steel building went from sealed engineering drawings to a 3D design to the finished welding shop. Watch the whole sequence, then see the finished building below.
How do you build a welding shop that can handle a Northern Ontario winter? This 80 x 100 x 27 ft clear-span steel building was engineered for heavy snow, crane work and future growth. The video goes from the sealed engineering drawings to the 3D design to the finished welding shop.
Design your own building the same way with the free 3D building designer: set the width, length, height, doors, lean-tos, roof pitch, colours and wainscot, then send it to a building consultant for an engineered price.
Want a building like this one?
Send us your size, site and how you will use it, and a building consultant will come back with an engineered quote.
Engineered for Thunder Bay: the design loads
Thunder Bay sits on the north shore of Lake Superior, with long, cold winters, heavy snow and open, windy sites. These are the design criteria from this 80x100 steel building's order and sealed drawings.
| Design criteria | Value |
|---|---|
| Building code | 2015 National Building Code of Canada (NBCC), which the Ontario Building Code is based on. Drawings sealed by a licensed Ontario engineer. |
| Ground snow load | 60.6 psf (2.90 kPa) |
| Roof snow load (design) | 56.9 psf (2.72 kPa), normal exposure, with snow drift loads included |
| Rain load | 8.4 psf (0.40 kPa) |
| Roof live load | 20.9 psf (1.0 kPa) |
| Wind | 1-in-50-year wind pressure of 8.15 psf (0.39 kPa), open terrain |
| Seismic | Low: Sa(0.2) = 0.061, peak ground acceleration 0.036, site class D (stiff soil) |
| Importance | Normal (importance factors 1.0 for snow, wind and seismic) |
| Collateral load | 4.5 psf for lighting, sprinklers and services hung from the roof |
| Crane sidesway limit | H/100 for the crane frames, so the runway stays aligned |
| Drawings supplied | Sealed permit drawings, sealed erection drawings, a sealed anchor rod plan with foundation reactions, and sealed foundation drawings |
See how we engineer every building on our engineering page, or read the Ontario Building Code (O. Reg. 332/12). More from Noah Sinclair, our in-house structural engineer.
Get loads engineered for your site
Every quote is engineered for the snow, wind and seismic loads where your building will stand.
Designing an 80x100 steel building for two 5-ton cranes
Two 5-ton cranes on one runway, designed in from day one.
An overhead crane changes how a steel building has to be engineered. Crane wheel loads, sideways thrust and impact go straight into the frames and foundations, so the crane is designed in from the start, not added later. This 80x100 steel building was designed for:
- Two 5-ton top-running, single-girder cranes sharing one runway, with pendant control and Class C service.
- A full-length runway from the first frame to the last, with crane beams supplied with the building.
- 68 ft between rail centrelines, 18 ft 6 in from the floor to the top of the rail and 3 ft 9 in of clearance under the rafters.
- Rod bracing in the roof and sidewalls to carry crane forces, and a frame sidesway limit of H/100 so the runway stays straight.
Crane rails, end stops and the cranes themselves come from the crane supplier. The most important step is to get the final crane data (capacity, wheel spacing, bridge and hoist weights) to your building specialist early, because the frames, crane beams and foundation reactions are all engineered from it.
The crane is designed into the frames from day one, not bolted on later.
Need a building sooner?
New clearance buildings from cancelled orders often sell by phone before they are listed. Call to hear about unlisted inventory.
Insulation, liners and a roof built for winter
Holding heat and controlling condensation in a heated shop.
A heated 80x100 steel building in Thunder Bay needs an envelope that holds heat, controls condensation and stands up to daily shop use. This building was specified with:
- A standing seam roof (24-gauge, Charcoal Gray) on high-thermal clips that leave room for up to 12 in. of blanket insulation.
- 12 in. of roof insulation and 8 in. of wall insulation.
- Full-height interior liner panels on the walls (Ash Gray) and a Polar White roof liner, which protect the insulation, wipe clean and brighten the shop floor.
- 26-gauge PBR wall panels in Charcoal Gray with Ash Gray trim.
- Northern-style gutters with 27 ft downspouts for spring melt.
- Three insulated, wind-rated walk doors with panic exit hardware.
Why an 80x100 clear span works for a welding and fabrication shop
8,000 sq ft with no columns in the way.
An 80x100 steel building gives 8,000 square feet with no interior columns, so large weldments, trailers and equipment can move anywhere under the crane. Here is how the layout supports the work:
- 27 ft eave height leaves room for the crane runway with clearance above the hook.
- Five 20 ft bays keep the framing efficient and the crane beams a practical length.
- Three 14 x 16 ft door openings and one 12 x 12 ft opening let trucks and lowbed trailers drive in.
- Six high-level 8 x 2 ft openings, 20 ft up the sidewalls, add daylight or ventilation above the work.
- A 25 x 30 x 12 ft attached office on one endwall, with its own 3:12 roof.
- An expandable endwall, framed so more bays can be added later without replacing it.
Plan your clear-span shop
Tell us your doors, cranes and layout, and get an engineered, code-compliant quote within 1 business day.
What to watch for when building in Thunder Bay and Northern Ontario
The issues that matter most north of Lake Superior.
After more than 40 years of engineering buildings across Canada, these are the issues we plan for on every Northern Ontario project, from a small garage to an 80x100 steel building:
- Snow load and drifting. Thunder Bay's ground snow load is far higher than southern Ontario's. Drifts build up against taller walls and where an attached office meets the main building, so drift loads have to be designed in.
- Frost and foundations. Deep frost means footings and piers must be designed for local soil and frost depth, using the anchor rod plan and reactions from the sealed drawings.
- Crane data timing. If a crane is part of the plan, confirm its specifications before the order is finalized.
- Permits. The City of Thunder Bay requires building permits for virtually all construction and now takes commercial and industrial applications online. Sealed drawings from a licensed Ontario engineer are what it expects to see.
- Condensation in a heated shop. Continuous insulation and liner panels help keep warm, moist shop air off cold steel.
- Delivery and erection season. Plan delivery to Northwestern Ontario and erection around winter conditions, and allow for cold-weather concrete if the foundation is poured late in the year.
- Welding shop requirements. Fire safety, ventilation and fume extraction are set by local code and fire officials, so involve them early.
Check the City of Thunder Bay's building permit requirements before you order, and see our steel buildings in Ontario page for more on Ontario codes and projects.
Thunder Bay's ground snow load is more than double Toronto's. Design for it, and for the drifts.
Building in Northern Ontario?
Get a quote engineered for your exact site, snow load and crane plans, within 1 business day.
What does an 80x100 steel building cost in Canada?
Starting prices, and what moves them.
New Toro steel building kits start at $26 per sq ft (CAD) in Canada and $19 per sq ft (USD) in the United States, and every building is quoted to meet the loads and codes for your location and use. For an 80x100 steel building, the biggest price drivers are:
- Snow and wind loads at your site. A Thunder Bay building needs much more steel than one in a low-snow area.
- Cranes. Crane beams, heavier frames and bracing add cost, and the cranes and rails are bought separately.
- Eave height. A 27 ft eave uses more steel than a standard 16 to 20 ft shop.
- Insulation and liner panels.
- Doors, windows and framed openings.
- Attached structures, such as an office or lean-to.
- Delivery distance to your site.
The building kit doesn't include the foundation, erection, cranes or crane rails, so budget for those separately. Explore other sizes on our steel building sizes page, such as a 50x100 or 100x200.
Need a building sooner, or for less?
New, unused clearance buildings from cancelled orders are engineered for your site like any Toro building.
Why businesses choose Toro for engineered steel buildings
More than 40 years and 100,000+ buildings.
- More than 40 years supplying pre-engineered steel buildings, with more than 100,000 buildings sold.
- In-house engineering, with every building designed for the snow, wind and seismic loads at its exact site and shipped with engineer-stamped drawings.
- Precision laser-cut components that arrive ready to bolt together, for 30 to 50% faster construction than conventional wood framing.
- Clear-span red iron frames for wide, column-free shops, warehouses and plants, like this 80x100 steel building.
- A 25 to 40-year paint warranty on straight-wall buildings, depending on panel and finish.
- Ontario offices in Markham and Oshawa, with building specialists who speak English, French, Spanish, Portuguese, Italian, Persian and Chinese.
Start your quote
Tell us your size, site and use, and get a free quote engineered for your loads and code.
How this building came together
Toro engineers and supplies the kit; the owner's team builds it.
Specification and 3D design
Toro and the ownerSize, cranes, doors and insulation set, then modelled in 3D to confirm the layout.
Engineering
ToroDesigned to NBCC 2015 for the Thunder Bay site, sealed by an Ontario engineer.
Permit and foundation
Owner or contractorDrawings submitted for permit; foundation built to the sealed reactions.
Delivery
Toro ships, the owner unloadsThe complete kit shipped to Thunder Bay.
Assembly
Owner or contractorFrames, crane beams, panels and liners bolted together on site. Toro doesn't install.
The building consultant who sold this building
Every Toro building has one consultant from first call to delivery.
Nick Levy
Building Consultant · Toro Steel BuildingsNick Levy sold this 80x100 steel building and worked with the owner from the first specifications through engineering and delivery. He helps customers across Canada and the U.S. plan everything from garages and workshops to large commercial shops.
More buildings Nick Levy has sold
30x54x14, Whitefish ONCharcoal steel shop in Northern Ontario
40x60x18, Easton WAEngineered for heavy Cascade snow
40x60x16, Cochrane ABShop in the Alberta foothills
35x54x15, Paradise Hill SKPrairie shop and storage
40x85x14, Linden TNLarge steel building in Tennessee
16x99x15, Selden NYCommercial parking cover with solarTalk to Nick about your building
Get an engineered quote for your size, site and loads, ask about new and unlisted clearance inventory, or see Nick's past projects.
80x100 steel building FAQs
Still planning your build? Price your building and a building consultant will walk you through it.
How big is an 80x100 steel building?
An 80x100 steel building has 8,000 square feet of floor space. With clear-span red iron frames there are no interior columns, so the whole floor is usable for fabrication, equipment, vehicles or storage. This one in Thunder Bay also has a 27 ft eave height and a 25 x 30 ft attached office.
How much does an 80x100 steel building cost in Canada?
New Toro steel building kits start at $26 per sq ft (CAD) in Canada and $19 per sq ft (USD) in the United States, and every building is quoted to meet the loads and codes for your location and use. Snow load, cranes, eave height, insulation, doors and delivery distance have the biggest effect on the final price.
What snow load is a steel building designed for in Thunder Bay?
This Thunder Bay building was designed for a ground snow load of 60.6 psf (2.90 kPa) and a roof snow load of 56.9 psf (2.72 kPa) under the 2015 National Building Code of Canada, with drift loads included. Every Toro building is engineered for the snow load at its own site, so your numbers depend on your exact location.
Can a steel building support an overhead crane?
Yes, when the crane is designed in from the start. This 80x100 steel building was engineered for two 5-ton top-running cranes, with crane beams, heavier frames, rod bracing and foundation reactions all designed from the crane data. Share your crane specifications with your building specialist before the order is finalized.
Do I need a building permit for a steel building in Thunder Bay?
Yes. The City of Thunder Bay requires building permits for virtually all construction and accepts commercial and industrial applications online. Every Toro building comes with drawings sealed by an engineer licensed in the province, which is what building departments typically ask for.
What foundation does an 80x100 steel building need?
The foundation is designed and built locally for your soil and frost depth, using the anchor rod plan and column reactions on the sealed drawings. In Northern Ontario, frost depth and crane loads both affect the footing design, so involve your foundation engineer early.
How long does it take to build an 80x100 steel building?
Delivery of a Toro building kit usually takes 2 to 8 weeks, and your building specialist confirms timing. The components arrive precision-cut and ready to bolt together, so construction is typically 30 to 50% faster than conventional wood framing.
Is a steel building a good choice for a welding shop?
Yes. Steel framing and panels are non-combustible, clear-span frames leave the floor open for large work, and the building can be engineered for overhead cranes. Liner panels protect the insulation and keep the interior bright and easy to clean.
Keep reading
Related building types
Manufacturing facilities | Steel workshops | Steel warehouses | Commercial steel buildings | Red iron steel buildings
Planning a shop like this?
Toro Steel Buildings engineers your kit for your site's snow, wind and crane loads, with a quote within 1 business day.